Thursday, May 01, 2008

Rehabilitation of Afsin-Elbistan- A Thermal Power Plant



The meeting to be held between EUAS and the World Bank postponed to 28 April 2008. Latest status of the tender will be reviewed and the course to be followed for construction of the project will be examined. Letter from Hitachi group will be considered as well

The General Directorate of EUAS (Electricity Generation Corp.) which, after a preparatory period of 3 years, could not collect any bids for its Afsin-Elbistan A Thermal Power Plant Rehabilitation Project for which international feasibility studies were carried out as the most important project that will boost power generation in the public sector on the basis of local resources in anticipation of the power crisis which is highly likely to be experienced in Turkey in the year 2010 and for which credit financing was created by the World Bank after being approved from the standpoint of its being an exemplary project in the privatization of power plants, has re-focused its activities to determine the course it will follow henceforth under its project.

It is reported that the General Directorate of EUAS will first negotiate with the World Bank that extended EUR 280 million credit for the project, and obtain the opinion of the Bank in order to determine the steps it will take from now on for its turn-key international tender for Afsin-Elbistan A Thermal Power Plant Rehabilitation Project for which no price offers could be collected by 15 April 2008.To this end, it was reportedly decided first to hold a meeting on 24 April 2008, postponing it later on to 28 April 2008, Monday.

As might be recalled, Japanese Hitachi Group had submitted, instead of a bid, a letter stating that it is closely interested in the tender and requesting that a meeting be held for Afşin-Elbistan A Thermal Power Plant Rehabilitation tender for which price offers were requested by 15 April 2008

Latest status of the tender will be considered at the meeting to be held with the World Bank

Sources state that the General Directorate of EUAS will, prior to applying to the Board of Directors for the course to be followed under the project, examine the latest status of the tender with the World Bank at the meeting where the opinion of the Bank will be obtained as well.

As is known, EUR 280 million credit agreement signed with the World Bank in 2007 foresaw that the rehabilitation operation would be realized according to the international tender procedures of the World Bank, as approved under related feasibility studies. In fact, action has so far been taken by obtaining the approvals of the Bank at such important stages as bid invitation, bid evaluation under the tender issued according to international criteria.

When reviewing the latest status of the tender, the letter from Hitachi group will be considered as well, and Hitachi group’s proposals concerning the performance guarantees may be discussed at this point, sources say.

Sources state that the General Directorate of EUAS expected Hitachi Group to submit a bid, that submission of a letter instead of a bid is an unexpected development for a potential customer, that for this reason, the General Directorate of is not warm towards the letter of Hitachi Group, and stress that Hitachi Group could not exploit an important chance.

As is known, the General Directorate of EUAS can hold “Package System” tenders as well, besides the international turn-key tenders. EUAS can invite bids for each of the main items of big projects in the form of a separate package, thus collecting “Package System” bids, and can commission the plant concerned without any problems by monitoring the project coordination rigorously and by ensuring harmonization among the activities concerned. Signing contracts with specialized contractors as well, the General Directorate of EUAS is known to prefer turn-key contracts over the contracts made with specialized contractors in order to be able to commission the plant concerned with less problems.

On the other hand, the meeting to be held with the World Bank will consider the issue of the new price increases being taken into account in the realization of the project and whether there will be an increase in the total investment cost in such a case.

As is known, the Undersecretariat of the State Planning Organization (SPO) is extremely sensitive towards the total investment cost, emphasizing that there are certain investment limits in order for the rehabilitation investment to be feasible. It is reminded that, if the total investment cost is to be increased, it will be subject to the favorable opinion of SPO and to the approval of the Supreme Planning Council.

The project was foreseen to be completed in 2009 from the standpoint of security of electricity supply

Afsin-Elbistan A Thermal Power Plant Rehabilitation Project had been selected, from the standpoint of the World Bank as well, as the rehabilitation project with the highest efficiency for the Generation Privatization applications to be launched in the coming period.

Included in the public investment program in the year 2006, Afşin-Elbistan A Thermal Power Plant Rehabilitation Project is Turkey’s most important investment to be commissioned from the standpoint of the security of electricity supply in the year 2010. Foreseen to be completed by the year 2009, the project has already been delayed for about 1 year, and, due to this development under the tender, the course to be followed will be determined urgently in order not to lose more time for construction of the project, sources say.

Sunday, February 10, 2008

Lessons Learnt from a Lost Order – 1994, DilOvasi- Istanbul

Dear Energy Professional, Dear Colleagues,

The Client was a very successful Turkish businessman, second generation industrialist, owning and operating the biggest private Turkish Iron &Steel Mills in DilOvasi Istanbul, where he was/still is fabricating steel rebars for the construction industry. He was educated in Robert College in Istanbul. Below is my story (or detailed report) of my years in 1994 trying hard to sell industrial size steam boiler(s) to the Client, but in the end we failed due to unnecessary third party company politics.

Your writer brought together a number of past “Minutes of Meetings” which were depicting a period of more than one year. You will read business minutes one after another, some very dull/ some too technical/ some too complicated in details, but we hope that in the end it will give you an inside feeling of world corporate life. Dates/ times/ places are real, although we tried to keep our Client anonymous.

On 8th September 1994, we (your writer and BWG's Expatriate JV General Manager Mr. Don Lee McKenzie) on behalf of USA Parent company were invited to have a meeting with The Client upon our request and deliver the US parent company invitation letter to North American offices, to enable him to visit our US fabrication and site installation facilities.

Prior to this meeting we had the opportunity to speak with his Project Manager for the latest status. He explained that The Client has already placed the order for two each Frame-9E and one each steam turbine to have S209E GE combined cycle. The HRSG is to be purchased now. The interested parties were Noother/Ericson, Deltak, Vogt, SBB, Ansaldo, CEI/Italy, Standardkessel, AE&E/Austria, CMI/Belgium and B&W. Some of them already delivered preliminary budget configurations and 3-4 of them have had comprehensive discussions regarding their offerings. Our USA parent company was also in their vendor list.

In the meeting that followed with The Client, his Deputy General Manager in charge of Energy joined us. They explained the history of the project. In order to be free from electricity interruptions and high electricity tariff, they wanted to purchase one simple cycle Frame-9e just sufficient to cover their requirements. Public offices pressured him to change it into combined cycle, so they then investigated to purchase the necessary Steam turbine and the HRSG. Due to economics of scale, two gas turbine plus two HRSG plus one steam turbine (S209E) were very attractive in unit US Dollar/KW price compared to smaller size, 1GT+1HRSG+1ST combination.

This time they faced with the danger of unavailable natural gas supply from Russia. Algeria natural gas was already allocated for other purchasers. Middle East supply prices were relatively expensive. Central Asia could not be reached in near future. Therefore they also investigated other fuels to be fired in the gas turbines. Other than natural gas and distilled oil, they also required their GT supplier company to install necessary equipment to fire heavy fuel oil (#6) in gas turbines. Because of growing lack of confidence in natural gas supply from Russia, it was required to have the HRSG(s) with fuel oil nr.6 handling capability as the major fuel not back-up.

They also were investigating how to purchase a good, reliable, economically priced HRSG in very short period of time. The HRSG time table was before the arrival of the selected steam turbine to The Client site in Istanbul which was scheduled by the end of June 1995.

Here were the major issues discussed in our meeting to be resolved,

- Could our US parent company design and manufacture an unfired HRSG capable of handling the exhaust gas coming from Fueloil nr.6 firing GE Frame-9E gas turbine? Any references?
- Any other US HRSG supplier reference?
- European suppliers warned them that in natural circulation design HRSG, it was very difficult to clean the soots in the boiler since they accumulated and could not be cleaned easily whereby in forced circulation soot blowing and water washing was easy from top. We believed that there was no sense/ no reasoning in this warning but anyhow we had to clarify in written that Natural circulation was also suitable while fueloil nr.6 is fired in gas turbines. Our North American references were to be investigated.
- Manufacturing and site installation of the selected HRSG in Turkey. The Client disclosed that other suppliers advised them 35,000 man-hours (in North American or West European standards) to be spent for one each HRSG. If they pay 3 US$/mh bare cost to their workers whereby the North American per man-hour was around 50 US$/mh. Therefore it was more economical to make the fabrication in Turkey as long as it was certified. That means they had no objection for fabrication in our Ankara plant. We could also reduce the cost for local supervision on local fabrication.
- This was discussed with much interest. They reiterated that it was not their intention to get involved in boiler business. Their intention was to receive the lowest cost for the best available quality.
- Labor productivity was also a major issue. If an European company manufactures one HRSG unit in 35,000 MH, the same could be handled in The Client machine shops maybe twice as much. We estimated almost same productivity in our local fabrication workshops for similar fabrication. However US Parent company advised tentatively to spend approximately 13,000 North American man-hours for a modular type one similar HRSG for the same purpose.
- Conceptual design of the power plant was to be carried out by the nominated GT supplier company. Detail engineering would be handled by an A/E consultant company in North America. HRSG Engineering should be done in North America. Our US parent company should handle all necessary design and major engineering. The Client prefers a ready-made off-the-shelf design to reduce the engineering cost. We explained that our HRSG design was ready-make modular type, and a marginal additional engineering activity was required for the new applications.
- They were looking for a Hybrid-Contract to reduce the cost. Cooperation and/or partnership was expected. They did not intent to make formal tender, but wanted to select one company for intense discussions and business negotiations. Our local Ankara shop fabrication was preferable since we had the necessary boiler fabrication facilities, ASME stamp, experience etc.
- The Client wanted to carry out what they know best. It was manufacturing rod bars for civil construction. Therefore we would be of most interest to them if we could verify the relative cost savings..
- HRSG delivery schedule was extremely important. They had to finalize everything by the end of 1994. They needed everything to be delivered before the end of June 1995, since then Steam turbine would arrive to the site and they had to deal with site installation of the steam turbine. Before the arrival of steam turbine, site installation of both two units of HRSG had to be completed at site.
- The Client preferred all seamless tubes. They were in Kentube/ Tulsa OK to investigate the fabrication, price and delivery conditions. They investigated also in Europe and concluded that seamless finned tubes could be supplied from Europe with the same prices as of welded type finned tubes supplied from North America. The Client had regular shipping between his Istanbul sea port and North Sea European sea ports in every 33 days. They were importing scrap steel for his plant and exporting fabricated rod iron to international markets. Their seaport facilities were underutilized. The price for shipping from North Sea European ports to Istanbul was 17 US$ per ton in year 1994. Whereby from North America they could not control the ocean transportation costs.
- Deputy general manager in charge of Energy requested a detailed list of fabrication tasks for the HRSG supply. Each individual task had to be identified with estimated time period. Estimated percentage in man-hours in the total scope to be identified. Not necessarily as pressured non-pressured parts but each individual task.
- They were pretty comfortable with the current performance of GT supplier in this project.
- Currently they had reached to generate 365-370MW electricity output in simple cycle. After completion of the current CCPP project, the next project was an extension with additional 220MW gas turbine plus necessary HRSG and the steam turbine to reach an overall capacity around 700 MW. They were also investigating the purchase of nearby electricity distribution within the privatization scheme.
- However they had not realized the electricity sell agreements with TEAS (electricity generating company), gas purchase agreement with Botas (public pipeline company). These were carried out by their Ankara office, not yet finalized, but expected soon.
- They were carefully watching the other development in the same field. Enron, Unit etc. However they would like to follow good examples and avoid the mistakes made by others. However they presume that at that time they were the front runner and they were uncomfortable of being the front runner.
- They feel that there might be in no need for a diverter valve. If it was necessary then the whole unit might be shut-down.
- They needed 2-3 weeks more to receive the latest tender documents, design parameters as prepared by Nominated GT Supplier Company and GT supplier company was going to sublet this activity to an A/E company. Short listed companies were Stone & Webster, Black&Veatch and CRS Sirrene Engineers (SC). Fine blue prints of the power plant would be prepared by the selected A/E Company.
- The last final proposal would be requested by October 1st with a bid deadline of October 21. We recommended that US parent company would prepare the final proposal documents and sublets all fabrication and local site installation works to local JV in order to offer a reasonable economical priced offer. The Client said that they had no doubt about the reputation of US parent company in boiler business. The Client would receive the proposals and would like to negotiate with only one reputable company and finalize the order in a very short period of time. Therefore it was requested to quote with the least price with no additional negotiation margins since there might be no chance to negotiate.
- Other vendors had offered proposals and had detailed discussions technical and commercial based on known conditions of a S209E system. They should only need to modify and finalize their proposals in early October. We should utilize the time before October 1st to prepare ourselves to have joint proposal.
- We asked whether they would be interested to come to North America and visit Barberton and West Point. They explained that they had been to many HRSG fabrication facilities and they had enough site excursions. They were in Monsanto plant. They were not interested in any more visiting. Our Expatriate GM presented the invitation letter in written. They accepted the invitation and thanked.
- We have been informed that GE is to guarantee the overall performance of S209E configuration. Therefore they are drafting the necessary conditions for the HRSG suppliers.
- Additionally they were investigating the applicable sea water suction pumps from deep sea water at constant 15 degrees Celsius temperature. Necessary sea water suction is 20,000 m3 at 3 atu at the end of the pipe line of 1.5 km. Diameter of the pipeline is 1,75meters. 6 meter elevation existed. This is an additional request by The Client to be handled in friendship understanding. Action needed by USA from Engineering Contracts.
- Since the Client had a seaport with 30,000 ton per day loading/unloading capacity which mean 10 billion tons per year. 50% efficiency means 4-5 billion tons per year. The Client was using 1 billion ton per year. That was a very appropriate location, infrastructure was completed but the facilities were underutilized.
- In order to utilize their sea port facilities, The Client was also interested in importing high quality coal and make additional CFB facilities. He asked us to furnish additional papers, documents on CFB for his personal information. That was not urgent. Action requested from our Expatriate JV GM.
- We believed that local partner’s support for fabrication and site installation estimation assistance were deemed necessary.

The Client meeting in Istanbul on Sep 23, 1994

We had the opportunity to meet the Client’s senior staff in their Istanbul office 5th floor meeting room on September 23,1994 Friday afternoon between 14-16 hours. participants were Their Deputy General manager in charge of Energy (Graduate of Brown University in USA, plus MBA), Project manager, former deputy General manager of Yarpet (Graduate of ODTU, chemical engineering), me, our Expatriate GM, Expatriate Project Manager from USA partner company Mr. Don Lee McKenzie.

Their DGM explained the latest status of the project as follows,

Conceptual design and overall guarantees of the combined cycle are by GE. Detail design by Stone and Webster (initially through UK office, then Boston office). Fuel is ash bearing oil (or fuel oil nr.6) plus natural gas. The retrofit on existing GT for fueloil conversion is currently carried out at site, the other started in fabrication plant.

HRSG soot cleaning is important, should be easy, with no interruption, flexible and simple. Initially they inclined to purchase only natural circulation design HRSG. But soot cleaning was an issue to be clarified. Preheating of boiler feed water was necessary in fuel oil firing. Seamless tubes from USA were expected to have 10-12 week lead time. There would be no diverter valve in the system. Take-out elbow would be removed after installation of HRSGs.

Their budget for turnkey scope as estimated for European suppliers was around 4 million US$. The serious parties were Italians with N/E and Vogt licensees, Standardkessel and Stein of France (GEC Alshtom). French and Italians were better in estimated lump sum prices. Our advantages were expected to be as follows

1. Expected economical price,
2. Shorter lead time,
3. Local close proximity. (Language, local response)

HRSG Pressure levels were 81, 7.6, 2.3 bars (1174, 110,34 psig). Competitors declared 33,000-37,000 MH in fabrication per HRSG unit. Our US parent Company estimates were 44,000 MH per unit, plus 1.5 factor for local fabrication. We also advised that Labor plus Overheads here were less than 15 US Dollars per man-hour versus 50 US Dollars per man-hour for Europeans.

We understood that The Client owned 100% of the company but has a democratic management. There were 3-4 senior managers to take the purchasing decision.

The advantages of having an order in The Client were specified as follows,

1. New and the first reference that size in Turkey
2. Reliable customer, no cash difficulty
3. First BOT example in Turkey
4. Opportunity to work together with GE and S&W.

They were a cash-rich company- not geared up with big organization, limited bureaucracy, however in need of qualified technical personnel to handle the incoming works.

From order to testing, tentative HRSG lead time was expected to be 13 months plus 1 month for testing. An accelerated schedule was under investigation. We expected to have less time for overall schedule. We would carry out fabrication and site installation. Drums were on the critical path (8-9 months). Sequencing the operation at site was important. Gas turbine was expected at site in June, site installation by October, and early operation in November.

Contract would be in private negotiation in Istanbul with maybe no tender spec at hand.

We requested to meet with the Client once more on next Friday morning September 30,1994. Their DGM promised us to advise the confirmation on Tuesday. In that meeting we should deliver the latest accelerated schedule. This meeting would afford excellent opportunity for the Client to gain needed comfort with Expatriate PM and US PARENT COMPANY (USA).

The meeting with The Client in Istanbul on Sep 30, 1994

We had one more opportunity to meet with the Client and his senior staff in their Istanbul office on September 30,1994 Friday between 10-14 hours. Our agenda was to establish a mutual meeting between our Expatriate Project Manager and The Client and have further discussions on HRSG and if possible on future CFB for the same enterprise. Participants were Expatriate Project Manager for US PARENT COMPANY/ HRSG, me and our Expatriate General Manager,

The Client expressed their pleasure to see us again in his office. Our Expatriate GM explained that the reason to ask for a new meeting was in order to introduce our principal from US Parent Company in charge of HRSG to The Client since we had no opportunity for a direct contact in the last meeting.

That should be a sincere and serious indication of US Parent Company to work and serve for their Combined Cycle project. It should also indicate our repeated reinforcement for concern over their heavy oil firing requirements in their units. We also appreciated their best quality, best delivery and best price objectives.

The Client explained their current status. They would consume 840 million KW-h in year 1994 and expect to consume 900 million kw-h in the next year. By taking the averages it was approximately 97 MW non-stop power consumption for his own plant.

They further explained that they have received the investment incentive certificate on Thursday (the day before Sep 30) from Turkish State Planning Organization to initiate the payment conditions, and today they paid the down payment to GT supplier company through their banks. That would speed up activities in GT supplier.

He additionally complaint the Botas (Turkish Pipeline Inc. a public monopoly on natural gas distribution) policies that they are purchasing natural gas from former USSR for 76-78 US Dollars per 1000 NM3 and selling to domestic consumers for 120 US Dollars per 1000 NM3. That was not fair.

They also requested more information on natural circulation horizontal design HRSG in fuel oil nr.6 firing in Gas turbines.

Our Expatriate Project manager presented a paper expressing the Considerations for Oil Fired Flue gas in Boilers and HRSGs, Basis of our Oil Fired Experiences, Our Recommendations for Heavy Oil HRSG, and The Client HRSG Schedule (tentative)

The Client expressed that they would be more comfortable if we could handle overall delivery period less than 11 months. He advised us that we should work 4- shift workdays. That means 3 times 8-hour shifts per day and the 4th shift as interchanging for weekends to enable non-stop work for 7 days per week.

Contract would be as simplest as possible. With GT supplier it was 5 pages. He says that he is known as a hard bargainer but he does not enjoy bargaining either. The current project was a show case for GT supplier, and will be also interesting for us. We agreed. We expressed that we should handle the scope split between US and Our local JV Company in internal agreements how to carry out the project. We were flexible to get the project done.

In the draft of the contract US Parent Company was to address necessary corporate positions that we need to address. Plus project explanations etc. We would make world wide sourcing to deliver the best economical third party purchases. Important Note: Writer does not recommend any attribution to third world and East European sourcing. Avoid.

The Client enquired any Software packages for I&C. Our Expatriate PM responded that it needs very simple package which can be incorporated within existing overall plant DCS system. We advised the architect of DCS system how to configure the HRSG I&C scope. No problem.

The Client disclosed that they have received a number of estimated proposals from North European (CMI/Belgium??, Stein/France??) and South European (Ansaldo or Belleli/Italy??) suppliers. These FOB proposals were well around 4.5 million US Dollars. With local The Client fabrication participation, it might be as low as 3 million US Dollars FOB basis.

The Client had also requested us to estimate a lumpsum figure for our proposal for 3 pressure level HRSG. Our Expatriate PM estimated maybe under FOB 5 million US Dollars per unit excluding site installation.

The Client asked the average proposal promotion period and estimated an average 6-month period. He explained that the proposal promotion period would be too short in his case after he agreed to negotiate with a reliable and competitive party.

The Client told that the situation was quite encouraging on payment side but current uncertainties were discouraging. The Client was waiting for our final offer for the applicable HRSG.

The Client said that they were ready to talk and discuss and negotiate. HRSG was on the critical path. It was the last and the most important piece in the combined cycle project. The steam turbine was expected to be at the site on June 1995. Site installation of ST was expected to be finalized in October 1995.

We might ask options from third party suppliers for accelerated deliveries and early purchase orders with preagreed cancellation charges. The Client Group had regular shipping schedule from Rotterdam every 35 days and from New York every 45 days.

His payments terms were preferably by irrevocable and confirmed letter of credit payable at the completion of the HRSGs, with no downpayment. That payment terms need cost of prefinancing while carrying internal penalty for late delivery case.

Our Expatriate PM estimated that it was too difficult to accept this payment condition without any downpayment. In GT supplier case, they were also receiving some sort of downpayment in order to initiate the activities at their head office.

The Client seemed like in non-stop negotiation on price, delivery and payment conditions for every instance and looking for any opportunity to take advantage.

We had to bring the Combined Cycle project negotiation opportunity to closure, outlining what we must do in next 2-weeks to secure negotiation, firm offer and meeting with NC before HRSG specs published. This was the window of opportunity presented to us by The Client.

We reached to the following internal conclusions

Objectives for Combined Cycle, was to get confirmation for a meeting with the Client on Oct.14 to make firm offer to negotiate. Our Board Member would be in Istanbul in that period. We could ask his assistance in this project.

Actions for Combined Cycle Proposal
HRSG configuration 2x5 or 3x4 and proposal design engineering
Combining local fabrication plant, construction and proposal support by local JV
Appointment with the Client and us on Oct.14, 1994
Schedule improvement and finalization in our local JV office
Timing for Combined Cycle ;
Our proposal review on Monday October 3, 1994 at 14:00 hours.
A meeting with The Client tentatively on Oct.14,1994.
Our firm quote by Oct 10th.

Our Expatriate PM to firm up offer and firm schedule and to make necessary travel arrangements to be in Istanbul on Oct.14,1994.

On November 7th 1994, we called The Client’s PM who has recently returned from USA. He declared that in the USA he had a number of meetings/ discussions to clear out disagreements. Energy balance of The Client Combined Cycle has not been finalized yet. A/E Company was responding quite slow. They had lay-offs, and GT supplier company was trying to make necessary engineering activities with limited number of engineers.

Functional specs were expected to be released by the end of November. Purchasing specs early December. Optimization for both fuels was deemed necessary. The calculated HRSG was currently giving more steam which could not be absorbed with the selected GE steam turbine.

As far as we understand their PM has tried to specify certain parameters to be inserted into A/E company Specs to clearly disqualify us. He advocated "Vertical gas flow" in HRSG tender specification in order to disqualify our design. A/E agreed that "Vertical gas flow" is also possible in natural Circulation. He did not hide his personal promotion of Assisted Circulation HRSG design. It was clearly understood that he is unfriendly (even openly hostile) to our approach.

But we knew that this was not appropriate to existing The Client demand. On the other hand our local fabrication plant promised to deliver their shop fabrication proposal early this week. Furthermore Local partner proposal department is expected to deliver their proposal sometime this week.

All these proposals were based on our 3x4 module natural circulation design assumptions. Moreover we believed that we should interfere the existing situation by more contacts with the Client himself.

DGM of The Client called me on December 12, 1994 and informed that they have received the tender specs from A/E Company recently. Specs are based on "Assisted Circulation" clearly. He asked me if we would be interested quoting an HRSG with "Assisted Circulation". I told him that we should see the specs first.

He then asked me to send someone to pick up the specs from his office this morning since they did not have secretaries to handle the copying and/or courier activities. He called once again and asked to send the person late that afternoon. They were making copies of the specs (10 copies at least) to distribute to interested other parties.

The Client’s DGM explained that since they have lost time during spec preparation in A/E company, they would like to place the HRSG order this month in December in order to utilize tax benefits of the year end.

With the sufficient inside assistance from The Client staff, an interested European company might be ready to furnish the appropriate proposal before the specs are issued, so that they could deliver their proposal in December and carry out necessary negotiations in so unfavorable time period for Europeans.

The Client might also favor them otherwise they were not so open to disclose Assisted Circulation. A/E Company might agree on better cleaning when Fuel oil nr.6 firing, the Client might have local fabrication cooperation with the selected party. Maybe they already agreed on how to proceed.

In the end we were disqualified with Forced draft circulation design condition since we did not have that design to offer, so we regretfully wrote the following letter to their A/E company later that week,

Ankara November 30, 1994
to A/E Company,
Istanbul District Sales Manager
Subj: HRSG(s) for The Client Combined Cycle Power Plant in Istanbul Turkey

Dear Sirs,
We have received information on the latest status of Ultimate Owner specs through our US Parent Company head office. It is understood that it will specify forced circulation HRSG and will be released to Ultimate Owner this Friday. Then Ultimate Owner will send the specs to interested HRSG vendors. There will be two weeks to bid. Operation is scheduled for October 1995. Ultimate decision maker is interested in us and recently brought to GT vendor's attention that this spec would eliminate our US Parent Company. Gas Turbine vendor stuck to their story that natural circulation, vertical tubes could not be backed up by them. However we understand that the senior consultant of Ultimate decision maker instructed the gas turbine supplier specifically to set up their plant equipment for forced circulation and vertical gas flow, and that is what they have done. We have seen some other similar influencers in the past for similar projects where consultants were actively promoting some specific parties whatever the real purpose, but these specific promotions they were not in parallel with the interests of the ultimate client. Action taken is so hostile to one specific party and so friendly to other we do not know why. I am afraid that project will turn out to be "Sell and Forget" procedures of some foreign parties and ultimate client would not receive necessary local service and maintenance on time regularly. Anyhow whoever is responsible for the decision, and sorry to say but I am afraid the enterprise will learn the verification in due time shortly in not so easy way. These are for your information only, Yours truly,

Later in time, we had been advised that the HRSG order was placed to Ansaldo Energia of Italy with forced circulation HRSG design to avoid any soot in oil firing, although plant was operated with natural gas only, never with fuel oil, at all times since then.

“What you are doing does not matter so much as what you are learning from doing it.” Proverb From an Ancient Egyptian Temple.

Don't count your chickens before they are hatched. /Turkish Preverb

Your comments are always welcome.

Friday, December 21, 2007

Triumph of a Trovatore in Ankara


Yuksel Soylemez The New Anatolian / Ankara/ 20 December 2007

Last Saturday 15 September 2008, the Minister of Culture, Ertugrul Gunay, and his wife, accompanied by their attractive young daughter, honored the State Opera by attending the first night of Verdi's 3 act opera, Il Trovatore in Ankara. Il Trovatore was first performed in Rome on 19 January 1853 and one hundred years later in Ankara in 1955.

This production was staged by Gurcil Celiktas, who earlier this year produced Nabucco with great success on a grand scale. His Trovatore is an even greater triumph for this seasoned Artistic Director of operas who had every right to be proud last Saturday night. The five great voices of the night were Senol Talinli in the lead role as the troubadour in love with Leonora, sung by Feryal Turkoglu, Eralp Kiyici as the Count Luna also in love with Leonora, but hopelessly, Sim Tokyurek as the troubadour's gypsy mother and last but very much not least the irreplaceable bass of the State Opera, famous for his Osmin in Abduction from the Seraglio, the one and only Tuncay Kurtoglu, as Fernando, the narrator soldier friend of the Count.

For some Il Trovatore, meaning the Troubadour, the singing minstrel, is the most lyrical of all the operas Verdi wrote because from beginning to end it is full of melodic arias, duets, quartets and choruses, which were trained and led by Italian Alessandro Cedroni to great heights. In my opinion, in this opera of Verdi the chorus has a greater part than in any other. The costumes by Nursun Unlu also deserve great applause and the simple sets were an effective foil to all the shining gold of the uniforms and richly colorful costumes. The orchestra led by Taner Bozok and conducted by Sunay Muratov attained its greatest heights without drowning the powerful singing. Each perfectly complemented the other.

The production was played to a full house at the State Opera with appreciation and applause, especially from the many young present who value this great talent we are so lucky to have in Turkey. The subject is love and superstition which takes place in a castle in Italy. Leonora, who was sung with great distinction by Feryal Turkoglu, is loved by two men, Manrico, sung by great tenor of the State Opera Senol Talinli with admirable gusto and stamina, and Count Luna, sung with his great voice by Eralp Kiyici, whose love is unrequited. Leonora is in love with Manrico who unknown to them is the brother of the Count, a fact revealed in the last act by the gipsy witch Azucena whose mother had been burned at the stake by the previous Count.

This first night was watched with appreciation and interest by the Minister and his family. On the whole, previous culture ministers with the exception of Istemihan Talay, regrettably have not in the past taken the trouble to attend State Opera productions and we very much hope to see much more of the Minister, busy as he is, at future productions of the Opera and Ballet and at classical music performances by our extremely talented orchestras and soloists. Earlier this year we saw Il Trovatore at Covent Garden, with La Scala and the Metropolitan one of the great opera houses in the world, and in our opinion this production was up to their standard in every way, presenting itself as an equal of the Covent Garden production. As I told her after the performance in her dressing room, Sim Tokyurek as Azucena was better than the one we heard at Covent Garden, not only with her voice but her stature also. She is certainly a rival with the great Jaklin Carkci for the title of Turkey's Azucena, where she made her name before going on to be a famous Turkish Carmen.

This first night gave an opportunity to talk to Ertugrul Gunay on Turkey's promotion in Europe with its classical music, opera and ballet. For that purpose I suggested with humility that Turkey's State Opera should tour German cities with Mozart's Abduction from the Seraglio. I suggested that Carmen, which Bizet wrote in French, should also be toured in France by the Istanbul Opera, and Nabucco, Trovatore or Traviata should go on tour in Italian cities. I also mentioned that there are several Turkish pianists living in the heart of Europe such as Idil Biret, Verda Erman, Huseyin Sermet, the Pekinel sisters, flautist Gulsen Tatu and there should be no inferiority complex about these high standard internationally recognized musicians, who are already very active all over the world as well as in Turkey, and could be sponsored by the Turkish private sector together with the Ministry of Culture to give concerts in towns all over Europe.

I told the Minister that it will primarily be the Ministry of Culture which will lead Turkey into Europe. The road to EU membership is paved with cultural manifestations and identity. It is not too far-fetched to envisage and plan a cultural classical music mobilization, concentrating in Europe, coupled with Turkish films, painting, sculpture, poetry. Small groups, trios, quartets, quintets from the Presidential Orchestra, for example, should concentrate in giving performances in Germany and France in a year where most unfortunately the home of the Presidential Symphony is closed. The Frankfurt book fair is an ideal opportunity as a starting point for this long cultural march. All these activities which can be spread over a period of years can be organized with the contribution of the EU embassies in Ankara and Turkish embassies in Europe on a bilateral cultural exchange programme. Il Trovatore, for which the Italian Cultural Attache Angela Tangianu must also be congratulated, is an admirable example of Italian-Turkish collaboration, and on that opening night many Italians living in Turkey were present and expressed their appreciation and enjoyment of opera in Turkey.

This excellent production of Il Trovatore can be enjoyed again on 26 December, 9 and 28 January and hopefully on many occasions after that.

How many intellectual Europeans know that in five Turkish cities there are 5 opera houses staging operas in their original languages with Turkish subtitles? How many of these people know that there are 5 orchestras in Ankara alone, and provincial symphony orchestras and music groups mushrooming in many cities, not just Istanbul. The Aspendos and Mersin Festivals every summer are a wonderful opportunity for a cultural holiday for all music lovers, whether Turk or foreigners. There is no limit to the imagination if it is understood here in Turkey that Turkey's acceptance and integration culturally in Europe are a most important key to Turkey's EU membership at grass roots level, let alone in the eye of EU opinion and government leaders.

All that said, charity begins at home, and we urge the government to give more recognition and value to the first class talents that Turkey is producing in the world of classical music, opera and ballet. It is a sad state of affairs that the Presidential Symphony Hall has been closed since last spring for repairs which despite all promised dates have still not yet begun. While there must be proper homes and halls, artists and equipment for classical musicians and artists to operate, music is far more important that the comfort of armchairs. Classical music has never been a luxury commodity, that is not its nature. All too often we hear it said, very wrongly and inaccurately, that classical music is a "western Christian art". That is not true: not merely throughout Europe, but all round the world from Tokyo and Bejing to Cairo, to former Soviet Union countries such as Georgia, Azerbaijan, Moldova to towns all over the USA, to cities of Latin America such as Mexico, Lima, Caracas, Santiago, classical music, opera and ballet can be enjoyed as a human right of civilized countries, as food for the soul which reaches way past boundaries of religion and nationality, playing a unifyingly peaceful part with no violent scenes such as are all too often witnessed in the mass fanaticism of football matches. To sum it up, life is short, art is long. We ask our leaders to respect that.

Sunday, October 21, 2007

"Madama Butterfly" in Ankara Opera House


“Madama Butterfly” a masterpiece by Giacomo Puccini, is performed at the Ankara Opera House last night. "Madama Butterfly" is Puccini's the most famous opera and remains among the three or four most popular operas in the world.

Statistics indicate that Puccini's “Madame Butterfly” and “La Bohème” are among the most popular and often-performed compositions in the world, pieces that almost all opera houses around the world include in their repertoires at least once a year. This shows the popularity and value of Puccini,

Last night, performance was extraordinary.

Friday, September 28, 2007

Advanced Users Symposium


Dear Energy Professional, Dear Colleagues

Thermal power plant design software company has scheduled a new training session called „Advanced Users Symposium“ in Frankfurt on Oct 30-31, 2007.

The idea of this session is to provide information about “advanced software features” to our advanced users of our thermal Power Plant design software

You will find the course content and further information when you follow this link:

http://www.thermoflow.com/Training_Advanced_Schedule.htm

You can refer to the link on the Thermoflow website, in case that you require further information.